SPAIN: A complex multi-year programme to remodel the metre gauge Euskotren network around San Sebastián was completed on November 21 with the opening of a 4.2 km tunnel taking the Hendaye/Irun – Bilbao railway beneath the city centre, and for a short distance under the beach. The tunnel replaces the surface terminus at Amara with a deep-level station and a through line enabling services from Bilbao to run through San Sebastián and the conurbation covering the area from Lasarte-Oria to Pasaia, Errenteria, Irun and Hendaye across the border in France. The section between San Sebastián and the French border is known affectionately as El Topo (‘the Mole’). It gained its nickname over a century ago because of the tunnels comprising around 20% of the 29.8 km route. The cross-city tunnel saw its inaugural passenger train when the 06.35 T1 service ran through from Lasarte-Oria to Hendaye. It was low tide in the Bahía de Concha, so the first train to run in commercial service underneath the waves (albeit only for a few metres) was the 13.05 departure. The T1 service continued uninterrupted for 40 h until late on Sunday evening, reflecting the standard weekend pattern of El Topo operations. By the early 2030s, a further set of enhancements is envisaged to permit headways of 7½ min. Untangling El Topo Completion of the cross-city line beneath the beach is the latest stage of a long and complex history of reworking, rebuilding and realigning the Euskotren network around San Sebastián. In 2005, work started on the doubling of the 2.8 km section between Loiola and Errenteria. The bridge over the River Urumea just east of Loiola-Donostia station was rebuilt, and a 2 500 m double track tunnel bored beyond, parallel to the existing single track one. The tunnel, inaugurated on October 4 2012, has two underground stations at Intxaurrond and Herrera. The original tunnel, with its unusual ogive cross-section will in the medium term form the metre gauge access to the quays at Pasaia for freight traffic. This tunnel was followed by the construction of an underground section of line between Altza and Galtzaraborda, east of San Sebastián, which opened to traffic on July 18 2026. The bypass eliminated a bottleneck by avoiding the need for trains to reverse at Altza, which became a through station. Addressing Amara From around the turn of the millennium, plans were formulated to create a new alignment through Bentaberri to the Bahía de La Concha littoral, from where it would turn south and pass beneath the city centre to reach the surface just beyond Amara terminus. The first step was the construction of a 3.3 km stretch of railway between Añorga and Easo, just south of Amara terminus. Work began in 1998, and the double track line, almost entirely in tunnel, and with a new underground station at Lugaritz, was inaugurated on March 10 2005. The previous trackbed, including the 840 m Morlans tunnel, is now a footpath and cyclepath. The Variante Sur will serve eventually as a bypass line avoiding Amara for freight traffic. This work was followed by the doubling of the 1.8 km between the junction at Lasarte and Errekalde. The €9.5m scheme involved the boring of a 500 m tunnel, part of the 800 m of new alignment. Work started in early February 2010 and the line was put into service on April 10 2012. Simultaneously, work was in progress on the doubling and realignment of the 2.2 km between Errekalde and Añorga, with 955 m placed in tunnel. This €30m project, on which work started in August 2009, was co-financed by the Basque regional government (77.34%) and the Diputación de Gipuzkoa (22.66%). The new section was put into use on May 28 2012. Contracts let Meanwhile, the contract for the construction of the cross-city core was awarded in two parts, given the complexity of the work. Basque railway infrastructure authority ETS was responsible for the tendering, awarding and re-awarding of contracts. In September 2017, lots covering the boring of the 2.1 km of tunnel between Lugaritz and Miraconcha was awarded to Construcciones Moyua, Viuda de Sainz and Comsa for €38.1m. The work included the subterranean station at Bentaberri. The contract for the 2.1 km of tunnel from Miraconcha to Easo, including the stations at Kontxa-Zentroa and Amara-Easo, worth €53.2m, was awarded in December 2017 to Sacyr, Cavosa, Campezo, Mariezcurrena and Zubieder. The higher cost of this section was derived from the complex geology. This proved even more problematic than had been envisaged, and in early June 2020 the contract had to be terminated on account of the unstable fragmented rock encountered in a 40 m section under the square at Easo. Sand infiltration was also encountered where the tunnel ran under the beach. The resulting retendering took place and the following year a new contract, valued at €47.8m, was awarded to Altuna y Uria, Acciona and Iza. With the tunnel nearing completion, on December 14 2023 a consortium formed of Elecnor, Omexom Spain, Eldu and Montajes Eléctricos San Ignacio was awarded a €13.8m contract covering tracklaying, catenary, all electrical installations and signalling. When all was complete, with a delay of around two years, the construction of the new stretch of railway had turned out to be a costly exercise. The initial estimated bill, prior to tendering, in 2017 was €181.5m. In November 2026 it was announced that the final cost was €292m, a 60% increase. Various factors were cited as reasons, including the Covid-19 pandemic, and increases in costs of raw materials and labour, as well as the geological problems. Test running began on September 11 2026, followed by driver route learning involving 197 members of traincrew. San Sebastián’s Mole goes further underground, doubling service frequency
SPAIN: A complex multi-year programme to remodel the metre gauge Euskotren network around San Sebastián was completed on November 21 with the opening of a 4.2 km tunnel taking the Hendaye/Irun – Bilbao railway beneath the city centre, and for a short distance under the beach.
The tunnel replaces the surface terminus at Amara with a deep-level station and a through line enabling services from Bilbao to run through San Sebastián and the conurbation covering the area from Lasarte-Oria to Pasaia, Errenteria, Irun and Hendaye across the border in France.
The section between San Sebastián and the French border is known affectionately as El Topo (‘the Mole’). It gained its nickname over a century ago because of the tunnels comprising around 20% of the 29.8 km route.
The cross-city tunnel saw its inaugural passenger train when the 06.35 T1 service ran through from Lasarte-Oria to Hendaye. It was low tide in the Bahía de Concha, so the first train to run in commercial service underneath the waves (albeit only for a few metres) was the 13.05 departure. The T1 service continued uninterrupted for 40 h until late on Sunday evening, reflecting the standard weekend pattern of El Topo operations.
By the early 2030s, a further set of enhancements is envisaged to permit headways of 7½ min.
Untangling El Topo
Completion of the cross-city line beneath the beach is the latest stage of a long and complex history of reworking, rebuilding and realigning the Euskotren network around San Sebastián.
In 2005, work started on the doubling of the 2.8 km section between Loiola and Errenteria. The bridge over the River Urumea just east of Loiola-Donostia station was rebuilt, and a 2 500 m double track tunnel bored beyond, parallel to the existing single track one. The tunnel, inaugurated on October 4 2012, has two underground stations at Intxaurrond and Herrera. The original tunnel, with its unusual ogive cross-section will in the medium term form the metre gauge access to the quays at Pasaia for freight traffic.
This tunnel was followed by the construction of an underground section of line between Altza and Galtzaraborda, east of San Sebastián, which opened to traffic on July 18 2026. The bypass eliminated a bottleneck by avoiding the need for trains to reverse at Altza, which became a through station.
Addressing Amara
From around the turn of the millennium, plans were formulated to create a new alignment through Bentaberri to the Bahía de La Concha littoral, from where it would turn south and pass beneath the city centre to reach the surface just beyond Amara terminus.
The first step was the construction of a 3.3 km stretch of railway between Añorga and Easo, just south of Amara terminus. Work began in 1998, and the double track line, almost entirely in tunnel, and with a new underground station at Lugaritz, was inaugurated on March 10 2005. The previous trackbed, including the 840 m Morlans tunnel, is now a footpath and cyclepath. The Variante Sur will serve eventually as a bypass line avoiding Amara for freight traffic. This work was followed by the doubling of the 1.8 km between the junction at Lasarte and Errekalde. The €9.5m scheme involved the boring of a 500 m tunnel, part of the 800 m of new alignment. Work started in early February 2010 and the line was put into service on April 10 2012.
Simultaneously, work was in progress on the doubling and realignment of the 2.2 km between Errekalde and Añorga, with 955 m placed in tunnel. This €30m project, on which work started in August 2009, was co-financed by the Basque regional government (77.34%) and the Diputación de Gipuzkoa (22.66%). The new section was put into use on May 28 2012.
Contracts let
Meanwhile, the contract for the construction of the cross-city core was awarded in two parts, given the complexity of the work. Basque railway infrastructure authority ETS was responsible for the tendering, awarding and re-awarding of contracts. In September 2017, lots covering the boring of the 2.1 km of tunnel between Lugaritz and Miraconcha was awarded to Construcciones Moyua, Viuda de Sainz and Comsa for €38.1m. The work included the subterranean station at Bentaberri.
The contract for the 2.1 km of tunnel from Miraconcha to Easo, including the stations at Kontxa-Zentroa and Amara-Easo, worth €53.2m, was awarded in December 2017 to Sacyr, Cavosa, Campezo, Mariezcurrena and Zubieder. The higher cost of this section was derived from the complex geology. This proved even more problematic than had been envisaged, and in early June 2020 the contract had to be terminated on account of the unstable fragmented rock encountered in a 40 m section under the square at Easo. Sand infiltration was also encountered where the tunnel ran under the beach.
The resulting retendering took place and the following year a new contract, valued at €47.8m, was awarded to Altuna y Uria, Acciona and Iza. With the tunnel nearing completion, on December 14 2023 a consortium formed of Elecnor, Omexom Spain, Eldu and Montajes Eléctricos San Ignacio was awarded a €13.8m contract covering tracklaying, catenary, all electrical installations and signalling.
When all was complete, with a delay of around two years, the construction of the new stretch of railway had turned out to be a costly exercise. The initial estimated bill, prior to tendering, in 2017 was €181.5m. In November 2026 it was announced that the final cost was €292m, a 60% increase. Various factors were cited as reasons, including the Covid-19 pandemic, and increases in costs of raw materials and labour, as well as the geological problems. Test running began on September 11 2026, followed by driver route learning involving 197 members of traincrew.
San Sebastián’s Mole goes further underground, doubling service frequency