First wagons handed over for Tanzania – Zambia Railway revitalisation programme

Quick Read

AFRICA: The first of 300 container wagons for the Chinese-backed US$1.4bn Tanzania – Zambia Railway revitalisation project have been handed over by CRRC Qiqihar in Dalian ahead of shipping to Africa, and the Tazara board has approved a five-year strategic plan. The modernisation of the 1 860 km long, 1 067 mm gauge line from Dar es Salaam in Tanzania to Kapiri Mposhi in Zambia is being undertaken by China Civil Engineering Construction Corp under a 30-year concession agreement signed with the Tanzania Zambia Railway Authority in September 2025. Five-year plan approved As part of the implementation of the upgrading programme, the Tazara board approved a five-year plan for 2026-31 on October 12. This will see Tazara continue to operate freight services during the first three years of the concession period, while the concessionaire implements the investment programme. This covers US$1bn of infrastructure upgrades and US$400m of new rolling stock, including 12 locomotives and 762 wagons, of which the 60 tonne container flat wagons built by CRRC Qiqihar and handed over on November 24 are the first batch. Under the five-year plan, freight volumes on the line are projected to increase gradually from 110 000 tonnes in 2026-27 to 160 186 tonnes in 2027-28 and 234 103 tonnes in 2028-29. Following the completion of the three-year rehabilitation programme, the concessionaire will take over freight operations, with volumes projected to rise to 1.2 million tonnes in 2029-30 and 1.8 million tonnes in 2030-31. Tazara expects this increase in traffic to strengthen its financial position through concession fees and other earnings such as passenger services and property leases. Growth will also be supported by increased cargo volumes through the port of Dar es Salaam and mineral traffic from Zambia and DR Congo, with annual operating revenue for Tazara projected to reach US$30.2m by 2030-31. Significant improvements Speaking at the 19th Joint Transport Sector Review which was held at Mwanza in Tanzania on November 16-18, Tazara Managing Director Bruno Ching’andu said the railway revitalisation project would bring significant improvements to the infrastructure, introduce modern locomotives and wagons and enhance passenger services. Aims include increasing freight capacity from 200 000 to 2.4 million tonnes/year by the fourth year of the concession, increasing train speeds from 30 km/h to 70 km/h, cutting the freight transit time between New Kapiri Mposhi and Dar es Salaam from 10 days to three and offering transport costs 30% to 40% lower than road haulage. He said the rehabilitation and modernisation of passenger rolling stock would also contribute to safer, more reliable and more comfortable travel. The railway was originally financed by China and built by China Civil Engineering Construction Corp in the 1970s as a symbol of post-colonial development. Following extensive negotiations, a MoU to undertake a revitalisation programme was signed by the three countries’ heads of state in Beijing in September 2024. A further agreement covering a concession and Chinese government support was signed in Beijing on September 29 2025. See also Investment in people and control systems aims to boost TAZARA performance China-backed Tazara revitalisation officially launched TAZARA allocated funding as concession agreement awaited Tanzania seeks investors for standard gauge projects

AFRICA: The first of 300 container wagons for the Chinese-backed US$1.4bn Tanzania – Zambia Railway revitalisation project have been handed over by CRRC Qiqihar in Dalian ahead of shipping to Africa, and the Tazara board has approved a five-year strategic plan.
The modernisation of the 1 860 km long, 1 067 mm gauge line from Dar es Salaam in Tanzania to Kapiri Mposhi in Zambia is being undertaken by China Civil Engineering Construction Corp under a 30-year concession agreement signed with the Tanzania Zambia Railway Authority in September 2025.

Five-year plan approved

As part of the implementation of the upgrading programme, the Tazara board approved a five-year plan for 2026-31 on October 12.

This will see Tazara continue to operate freight services during the first three years of the concession period, while the concessionaire implements the investment programme. This covers US$1bn of infrastructure upgrades and US$400m of new rolling stock, including 12 locomotives and 762 wagons, of which the 60 tonne container flat wagons built by CRRC Qiqihar and handed over on November 24 are the first batch.

Under the five-year plan, freight volumes on the line are projected to increase gradually from 110 000 tonnes in 2026-27 to 160 186 tonnes in 2027-28 and 234 103 tonnes in 2028-29.

Following the completion of the three-year rehabilitation programme, the concessionaire will take over freight operations, with volumes projected to rise to 1.2 million tonnes in 2029-30 and 1.8 million tonnes in 2030-31.

Tazara expects this increase in traffic to strengthen its financial position through concession fees and other earnings such as passenger services and property leases. Growth will also be supported by increased cargo volumes through the port of Dar es Salaam and mineral traffic from Zambia and DR Congo, with annual operating revenue for Tazara projected to reach US$30.2m by 2030-31.

Significant improvements

Speaking at the 19th Joint Transport Sector Review which was held at Mwanza in Tanzania on November 16-18, Tazara Managing Director Bruno Ching’andu said the railway revitalisation project would bring significant improvements to the infrastructure, introduce modern locomotives and wagons and enhance passenger services.

Aims include increasing freight capacity from 200 000 to 2.4 million tonnes/year by the fourth year of the concession, increasing train speeds from 30 km/h to 70 km/h, cutting the freight transit time between New Kapiri Mposhi and Dar es Salaam from 10 days to three and offering transport costs 30% to 40% lower than road haulage.

He said the rehabilitation and modernisation of passenger rolling stock would also contribute to safer, more reliable and more comfortable travel.

The railway was originally financed by China and built by China Civil Engineering Construction Corp in the 1970s as a symbol of post-colonial development. Following extensive negotiations, a MoU to undertake a revitalisation programme was signed by the three countries’ heads of state in Beijing in September 2024. A further agreement covering a concession and Chinese government support was signed in Beijing on September 29 2025.

See also

  • Investment in people and control systems aims to boost TAZARA performance
  • China-backed Tazara revitalisation officially launched
  • TAZARA allocated funding as concession agreement awaited

Tanzania seeks investors for standard gauge projects

Source: Railway Gazette